|
Kumar & Associates, Inc. (K+A), performed geotechnical
engineering, environmental studies, and conducted the
construction
materials
testing and observation for the design of Invesco Field
at Mile High. The stadium, which was constructed at the
site of the old Mile High Stadium and McNichols Arena,
consisted of a circular reinforced concrete and steel
structure with an outside diameter of approximately 720
feet. The structure has six main floor levels, with the
lowest level floor matching the playing field elevation
and the uppermost floor at an elevation approximately
200 feet above the playing field elevation.
Straight shaft piers
drilled into the bedrock were recommended as the
preferred foundation type. Additional services
provided by K+A included geotechnical engineering
report addenda to address site utilities, ring road
pavement design, the pedestrian "Broncos Bridge"
over the South Platte River and pavement design for
Colfax/Federal interchange improvements; materials
management and health and safety plans; and
construction phase geotechnical engineering,
materials testing, and environmental services.
K+A provided Phase I
Environmental Site Assessment (NEPA Hazardous Materials
Study) services for the new stadium property. The Phase
I identified past usage of the property as a City and
County of Denver landfill. Based on that information, a
Phase II Environmental Site Assessment was performed
with the drilling of soil borings and installation of
ground water monitoring wells. Soil and ground-water
sampling and monitoring indicated that there were no
hazardous materials identified within the fill material
or ground water.
During excavation of the
landfill materials in the footprint of the stadium, K+A
provided soil sampling of field monitoring and submitted
samples for laboratory analysis to confirm that the
soils removed were not hazardous or above state approved
action levels for petroleum related compounds. By
evaluating geotechnical and environmental properties of
the fills and careful coordination between geotechnical
and environmental disciplines, 60-75% of the existing
fill materials were allowed to be reused in areas
outside the building, thereby saving hundreds of
thousands of dollars on this net fill import project.
During the excavation
dewatering for utility line construction, K+A provided
weekly sampling of discharge to storm sewers in
compliance with the project state NPDES permit.
Construction materials
testing services provided during construction included
observation of the installation of the drilled pier
foundation system. The drilled piers for this project
provided several challenges such as the presence of
ground water and lateral load concerns, which required
careful monitoring to be sure that the surrounding
supporting stratum was capable of resisting the lateral
forces. Other services provided included the
observation and testing of the mass excavation and fill
placement, post-tensioned slab system, reinforcing
steel, structural concrete, structural masonry,
fireproofing, site utilities, asphalt paving, and
structural steel fabrication and erection. |